How to quote a CNC machined part from a STEP file
What to read from the 3D model, the six cost blocks every machining quote needs, how quantity really changes the price, and a worked example with the numbers laid out.
Written by the team building Tiento Quote · Updated
Short answer: a CNC quote is the sum of six cost blocks: material, machining cycle, setup and programming, inspection, secondary operations and a manufacturability allowance. Price the per-piece blocks at the quantity you will actually manufacture, add the once-per-lot costs, divide by the quantity the customer receives, then apply your margin and check the result against your minimum order.
This guide is written for estimators and shop owners who already quote machined parts and want a repeatable structure, especially when the request arrives as a STEP file. It follows the same cost structure we use while building Tiento Quote.
1. What the STEP file tells you, and what it doesn't
A STEP model gives you exact geometry, which is enough to price most of the work:
- Bounding box: the starting point for the stock size.
- Part volume against stock volume: how much material you remove, which drives roughing time.
- Holes: through or blind, diameter, depth-to-diameter ratio, counterbores and countersinks.
- Pockets and slots: depth against width, internal corner radii, length against width.
- Faces you need to reach: how many setups the part needs.
- Thin walls and tight clearances: where the part becomes harder to make than its size suggests.
What the model usually does not contain: tolerances and fits, surface finish, thread specifications (threads are often modelled as plain holes), the material grade and temper, treatments, quantities and delivery dates. Those live on the drawing and in the request. A quote built from the model alone silently assumes general tolerances, no threads and no treatment, so write those assumptions on the quote.
2. The six cost blocks of a machining quote
Keeping the blocks separate is what makes a quote reviewable: when a price looks wrong, you can see which block is wrong instead of arguing about a single number.
Material. Price the stock, not the finished part. Size the blank from the bounding box plus facing and clamping allowance, snap it to the bar or plate sizes you actually buy, then multiply volume × density × price per kg.
Typical mistake: pricing the part's net volume. On a heavily pocketed block you pay for several times the metal that leaves the shop.
Machining cycle. Removed volume, adjusted for how the material machines, plus time for each feature: every hole is a tool change and an approach, every pocket a roughing and a finishing pass. Deep features are slower: blind holes much deeper than about three diameters need peck drilling, and deep narrow pockets need long tools and lighter cuts. Multiply the minutes by the machine's hourly rate.
Typical mistake: pricing by weight or envelope. Two parts with the same bounding box can differ several times in cycle time.
Setup and programming. Paid once per lot. Setup grows with the number of setups: each extra face to reach means another clamping, zeroing and probing. CAM programming grows with the number of features and with non-standard features.
Typical mistake: spreading it badly, quoting five parts at the unit price of a hundred, or the other way round.
Inspection. First-article inspection once per lot, plus per-piece checks. It grows with the number of toleranced features and with tighter tolerance classes.
Typical mistake: pricing zero inspection until the customer asks for a measurement report.
Secondary operations. Threading, deburring, anodising, plating, heat treatment, inserts and any external operation. External treatments carry the supplier's minimum lot charge and transport in both directions.
Typical mistake: forgetting the treatment's minimum charge on a small batch.
Manufacturability allowance. The expected cost of scrap and rework on features that are hard to make: small deep blind holes, thin walls, tight internal corners, long slots. Keep it as its own visible line instead of inflating the cycle time, so you can decide consciously whether to charge it, propose a design change or accept the risk.
Typical mistake: hiding risk in a margin that nobody can explain six months later.
3. Quantity: parts delivered against parts made
A quote has two quantities, and mixing them up is a common reason a "profitable" job loses money:
- Customer quantity: the conforming parts the customer orders and receives.
- Planned manufacturing quantity: what you will actually run, including spares for setup scrap, first-article checks and expected rejects.
Per-piece blocks (material, cycle, per-piece inspection, secondary operations, allowance) scale with the planned quantity. Lot costs (setup, programming, first article) do not. The unit price is the lot cost divided by the customer quantity, because that is what you invoice. If the lot total falls below your minimum order value, show the difference as its own line instead of quietly raising the unit price.
4. Worked example: an aluminium manifold block
A hydraulic manifold block in aluminium 6082, about 80 × 60 × 40 mm, with eight holes (two of them blind at five diameters deep), two pockets, machined from two sides and clear anodised. The customer asks for prices at 20 and 200 parts.
- Stock: 85 × 65 × 45 mm saw-cut blank, 0.67 kg at €6.00/kg ≈ €4.03 per piece.
- Cycle: 14 minutes at €70.00/h ≈ €16.33 per piece.
- Setup and programming: 2 setups of 45 minutes at the machine rate, plus 2.5 h of CAM programming at €60.00/h ≈ €255.00 per lot.
- Inspection: €35.00 first article per lot plus €1.50 per piece.
- Anodising: €3.00 per piece from the supplier.
- Allowance: €0.80 per piece for the two deep blind holes, where a broken drill scraps the part.
- Planned quantity: 21 made for 20 ordered; 204 made for 200 ordered.
| Cost block | 20 ordered21 made | 200 ordered204 made |
|---|---|---|
| Material | €84.58 | €821.66 |
| Machining cycle | €343.00 | €3,332.00 |
| Setup and programming | €255.00 | €255.00 |
| Inspection | €66.50 | €341.00 |
| Secondary operations (anodising) | €63.00 | €612.00 |
| Manufacturability allowance | €16.80 | €163.20 |
| Lot cost | €828.88 | €5,524.86 |
| Cost per delivered part | €41.44 | €27.62 |
The cost per delivered part falls from €41.44 to €27.62, about 33% less, and almost all of that comes from one block: setup and programming weigh €12.75 per part at 20 units and €1.28 at 200. Material and cycle time barely move per part. That is why each quantity break should be priced from the same build-up rather than with a flat discount.
Illustrative figures for a European job shop, before margin. They are not Tiento defaults, customer data or market benchmarks; use your own rates and supplier prices.
5. Checklist before you send the quote
- Stock sized to a bar or plate you can actually buy.
- Setups counted from the faces that need machining.
- Deep holes, deep pockets and thin walls checked and priced.
- Tolerances, threads and finish read from the drawing, not assumed from the model.
- External treatments include the supplier's minimum charge and transport.
- Planned quantity covers setup scrap and first-article parts.
- Lot costs divided by the customer quantity, not the planned one.
- Minimum order applied as a visible line.
- Assumptions written on the quote.
6. Where Tiento Quote fits
Tiento Quote automates the first half of this work. It reads the customer's STEP file, detects holes, pockets, slots, countersinks and counterbores, and applies the active estimate source, either the Tiento baseline or a calibration built from your reviewed historical jobs, which stays visible on every quote. DFM notes such as deep holes or thin walls appear as review guidance, separate from the priced total. The estimator keeps the last word: annotate features, adjust quantities, override the final price and export a draft or customer PDF.
The block-by-block build-up described in this guide, with separate customer and planned quantities, is what we are building next with our pilot workshops. See how Tiento Quote works.
Common questions
Can you quote a CNC part from the STEP file alone?
You can price the geometry: stock, removed volume, features and setups. You cannot price what the model does not contain: tolerances, surface finish, thread specifications, material temper and treatments usually live on the drawing or in the request. If you quote from the model alone, write those assumptions on the quote so the customer can correct them before the order.
What hourly rate should I use?
Your own fully loaded rate for each machine group: depreciation or lease, energy, floor space, maintenance, tooling and the operator time it actually consumes. A 5-axis machining centre, a 3-axis mill and a lathe should not share one rate. Copying a market figure hides whether a quote makes money.
Why does the unit price fall so much with quantity?
Setup, programming and first-article inspection are paid once per lot. On a small batch they can be the largest block per part; on a large batch they almost disappear, and material plus cycle time dominate. Quote each quantity break from the same build-up instead of applying a flat discount.
Should manufacturability risk change the price?
Only as a visible, deliberate decision. Deep small blind holes, thin walls or long narrow slots raise the chance of scrap and rework. Showing that allowance as its own line lets you choose between charging it, proposing a design change or accepting the risk, instead of burying it in the margin.